  1. According to the "Sustainable Development Roadmap for Listed Companies" issued by the Financial Supervisory Commission in March 2022, our company falls under the category of companies with paid-in capital below NT$5 billion. The parent company (individual entity) applies to Phase 3 of the GHG inventory (i.e., inventory to be completed in 2026, verification in 2028). The company will continue to follow relevant guidelines and regulations to manage the timeline for GHG inventory and verification disclosure.
  2. We plan to complete the GHG inventory and verification schedule for the parent company and the group (including subsidiaries) by the end of Q1 and Q4 of 2025, respectively, and submit for board approval.
  3. Disclosure content: Direct GHG emissions (Scope 1) and energy indirect emissions (Scope 2).
  4. Applicable timeline: The parent company applies to Phase 3, completing inventory in 2026 and verification in 2028. Subsidiaries in the consolidated report should complete inventory in 2027 and verification in 2029.
  5. The GHG inventory and verification schedule planning and execution timeline are shown in the table below, with progress reported quarterly to the Board as required.





 

Parent Company GHG Inventory and Verification Schedule Planning
TaskPlanned ScheduleCompletion Date

Set Inventory Plan

2025 Q1

2025 Q1

Set Verification Plan

Document Review Date

2025 Q3

 

Stage 1 Verification

2025 Q3

 

Stage 2 Verification

2025 Q3

 

 

Note: The parent (individual) company completed the GHG inventory in Q3 2025.

 

Group GHG Inventory and Verification Schedule Planning
TaskPlanned ScheduleCompletion Date

Set Inventory Plan

2025 Q1

2025 Q1

Set Verification Plan

Document Review Date

2026 Q3

 

Stage 1 Verification

2026 Q3

 

Stage 2 Verification

2026 Q3

 

 

Note: The group completed the GHG inventory in Q4 2026.

 

  1. As of April 30, 2025, the following GHG-related training courses and implementation status are described:
No.Course / Training / Briefing NameLocationOrganizerParticipants
1Carbon Management Platform Kick-off MeetingPurhui 2nd Floor Meeting RoomDingxin Computer6
2Business Travel Expense Reimbursement Module TrainingPurhui 2nd Floor Meeting RoomDingxin Computer3
3Category 3 Upstream Transportation Emissions ERP System TrainingPurhui 2nd Floor Meeting RoomDingxin Computer5
4Internal GHG Verifier TrainingPurhui 2nd Floor Meeting Room / External TrainingXinlianxiang Management Consulting Co., Ltd.11
5ESG Sustainability and GHG Carbon Management TrainingExternal TrainingTaiwan Public Vocational Training International Exchange & Development Association1
6Net-Zero Carbon Planning WorkshopExternal TrainingTaiwan Public Vocational Training International Exchange & Development Association1

 

  1. Currently, the company discloses GHG emissions for Scope 1 and Scope 2 as required. Considering that our company operates in the medical consumables manufacturing industry, some business activities and supply chain or external activities may fall under Scope 3. To enhance carbon management completeness, we will carefully assess the scope and method of future Scope 3 disclosure and gradually build the relevant inventory and reporting capabilities.